RAJ HILLS PHASE II
by SACHIN YAGNESHWAR PATIL
Individual
Project Information
RERA Certificate No.
P99000005109
Registration No.
REA99000011400
Registration Date
2017-11-13
Developer
SACHIN YAGNESHWAR PATIL Individual
Architect
James A Dias
Project Bank
THE SHAMRAO VITHAL COOPERATIVE BANK
Proposed Possession
2017-12-31
Revised Possession
2017-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1776.00 sq.m
Total FSI
1893.99
Approved FSI
1893.99
RAJ HILLS PHASE II
MahaRERA — P99000005109
MahaRERA — P99000005109
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors6
✅Sanctioned6
🚗Open
Parking13
🅿️Closed Parking10
📅Completion1900-01-01
Apartment Configurations
Raj Hills Phase Ii
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 1267.3 | 36 | 5 | 31 | 14% |
| 2 BHK | 185.55 | 4 | 4 | 0 | 100% |
| SHOP | 253.2 | 20 | 5 | 15 | 25% |
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 Bhk | 1267.300048828125 | 0 | 0 | 0 | 0% |
| 2 Bhk | 185.5500030517578 | 0 | 0 | 0 | 0% |
| Shop | 253.1999969482422 | 0 | 0 | 0 | 0% |
Construction Progress
RAJ HILLS PHASE II
RERA Registered Amenities
✅Aggregate area of recreational Open Space100%
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station90%
⬜Energy management
⬜Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting100%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting100%
✅Water Supply