Rani minnat enclave
by AMKB BUILDER AND DEVELOPERS
Partnership
Project Information
RERA Certificate No.
P99000012845
Registration No.
REA99000022728
Registration Date
2017-09-07
Developer
AMKB BUILDER AND DEVELOPERS Partnership
Architect
Vv&Associates
Project Bank
BANK OF BARODA
Proposed Possession
2018-12-15
Revised Possession
2018-12-15
Extended Possession
1900-01-01
Units Sold
0
Buildings
6
Project Area
3652.48 sq.m
Total FSI
3434.18
Approved FSI
3434.18
Rani minnat enclave
MahaRERA — P99000012845
MahaRERA — P99000012845
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors4
✅Sanctioned4
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors4
✅Sanctioned4
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors4
✅Sanctioned4
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors4
✅Sanctioned4
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors4
✅Sanctioned4
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors4
✅Sanctioned4
🅿️Closed Parking1
📅Completion1900-01-01
Apartment Configurations
A Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2bhk | 59.53 | 6 | 6 | 0 | 100% |
| 2bhk | 71.44 | 2 | 2 | 0 | 100% |
B Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1bhk | 35.76 | 8 | 3 | 5 | 38% |
C Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1bhk | 35.76 | 8 | 3 | 5 | 38% |
F Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1bhk | 35.76 | 8 | 5 | 3 | 62% |
Wing D
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1bhk | 34.51 | 6 | 3 | 3 | 50% |
| 1bhk | 35.1 | 6 | 4 | 2 | 67% |
Wing E
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1bhk | 35.76 | 8 | 3 | 5 | 38% |
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 34.5099983215332 | 0 | 0 | 0 | 0% |
| 1Bhk | 35.099998474121094 | 0 | 0 | 0 | 0% |
| 1Bhk | 35.7599983215332 | 0 | 0 | 0 | 0% |
| 2Bhk | 59.529998779296875 | 0 | 0 | 0 | 0% |
| 2Bhk | 71.44000244140625 | 0 | 0 | 0 | 0% |
Construction Progress
A wing
B wing
C wing
F WING
Wing D
Wing E
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station50%
⬜Energy management
⬜Fire Protection And Fire Safety
Requirements
⬜Landscaping & Tree Planting
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)90%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
⬜Water Conservation, Rain water Harvesting
✅Water Supply75%
