Project Information

RERA Certificate No.
P99000010882
Registration No.
REA99000018801
Developer
Rashmi Housing Private Limited
Project Bank
HDFC Bank
Proposed Possession
2024-12-30
Revised Possession
2024-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
19
Project Area
9587.81 sq.m
Total FSI
9587.81
MahaRERA QR
Rashmi Pink City Phase I
MahaRERA — P99000010882
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

Tpe W/2 L Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.02541
80%
2 BHK44.5550
100%
2 BHK50.6310100
100%

Tppe W/3A K Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.02532
60%
2 BHK44.5550
100%
2 BHK50.631091
90%

Type I/2A J Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.05550
100%
1 BHK33.161091
90%
2 BHK44.4550
100%

Type I/2B D Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.1615114
7%
2 BHK44.4505
0%

Type I/2B P WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.05550
100%
1 BHK33.161091
90%
2 BHK44.4541
80%

Type I/3A I Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.1610100
100%
2 BHK33.25550
100%
2 BHK44.4550
100%

Type I/3B E Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.1615015
0%
2 BHK44.4505
0%

Type I/4A W WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.05550
100%
1 BHK33.1610100
100%
2 BHK44.4550
100%

Type I/5A U WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.05550
100%
1 BHK32.42110
100%
1 BHK33.16990
100%
2 BHK44.4550
100%

Type P/1 H Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.16330
100%
1 BHK34.37440
100%
1 BHK34.74880
100%
2 BHK49.23550
100%
2 BHK50.53550
100%

Type P/2 F Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.16440
100%
1 BHK34.37550
100%
1 BHK34.74660
100%
2 BHK49.23550
100%
2 BHK50.53550
100%

Type P/2B O WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.16532
60%
1 BHK34.37541
80%
1 BHK34.74541
80%
2 BHK49.23550
100%
2 BHK50.53532
60%

Type Q/1 V WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK24.1515150
100%
1 BHK32.05550
100%

Type Q/1D B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.05523
40%
1 RK24.1515411
27%

Type Q1/C G Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.25550
100%
1 RK24.1515132
87%

Type W/3B A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.93550
100%
2 BHK50.6310100
100%
2BHK46.26550
100%

Type Y/4 C Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.1620155
75%
1 BHK34.37532
60%
2 BHK49.7532
60%

Type Z/1 Q WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.16532
60%
2 BHK44.4532
60%
2 BHK49.71082
80%
Commercial13.75101
0%
Commercial13.89101
0%
Commercial16.36202
0%
Commercial18.84101
0%
Commercial21.95101
0%
Commercial23.95101
0%

Type Z/1 R WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.05541
80%
1 BHK33.161082
80%
2 BHK44.4532
60%
Commercial15.13101
0%
Commercial16.36202
0%
Commercial23.95101
0%

Construction Progress

Tpe W/2 L Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Tppe W/3A K Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Type I/2A J Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type I/2B D Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type I/2B P WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type I/3A I Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type I/3B E Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor0%

Type I/4A W WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type I/5A U WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type P/1 H Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type P/2 F Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type P/2B O WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type Q/1 V WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type Q/1D B Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor0%

Type Q1/C G Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type W/3B A Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type Y/4 C Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type Z/1 Q WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Type Z/1 R WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station80%
✅Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths70%
✅Landscaping & Tree Planting20%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)80%
✅Solid Waste Management And Disposal
✅Storm Water Drains50%
✅Street Lighting50%
✅Treatment And Disposal Of Sewage And Sullage Water80%
✅Water Supply
✅Water conservation /Rain water harvesting