List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Raviraj Tarang

by Ravindra Shankar Sawant Individual
Certificate SignedP51800010482
Raviraj TarangProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800010482
Registration No.
REA51800021504
Registration Date
2021-09-09
Developer
Ravindra Shankar Sawant Individual
Architect
Neocon Infrastructure Services Pvt Ltd
Proposed Possession
2022-12-15
Revised Possession
2022-12-15
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
1315.30 sq.m
Total FSI
4262.00
Approved FSI
3358.00
MahaRERA QR
Raviraj Tarang
MahaRERA — P51800010482
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors13
✅Sanctioned13
🏗️Proposed Floors8
✅Sanctioned8

Apartment Configurations

RAVIRAJ TARANG A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL24.8914140
100%
RESIDENTIAL37.62761
86%
RESIDENTIAL39.81716
14%

RAVIRAJ TARANG B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL39.824222
8%
RESIDENTIAL43.061156
45%
RESIDENTIAL59.781174
64%
RESIDENTIAL67.35110
100%

RAVIRAJ TARANG C WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL34.21707
0%
RESIDENTIAL36.73707
0%

Construction Progress

RAVIRAJ TARANG A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RAVIRAJ TARANG B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RAVIRAJ TARANG C WING

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station95%
⬜Energy managemcnt
✅Fire protection and fire safety requirements90%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)90%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply85%
✅Water conservation /Rain water harvesting95%