REGENCY PALMS PHASE II

by REGENCY INC Partnership
Certificate SignedP52000021191
REGENCY PALMS PHASE IIProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000021191
Registration No.
REA52000057233
Registration Date
2022-06-22
Developer
REGENCY INC Partnership
Architect
Hiten Sethi Architects
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2025-06-01
Revised Possession
1900-01-01
Extended Possession
2025-06-01
Units Sold
0
Buildings
1
Project Area
4852.22 sq.m
Total FSI
22364.95
Approved FSI
22364.95
MahaRERA QR
REGENCY PALMS PHASE II
MahaRERA — P52000021191
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors34
✅Sanctioned34

Apartment Configurations

TOWER - B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
4BHK257.816133
81%
4BHK258.511091
90%
4BHK259.716124
75%
4BHK260.411064
60%
5BHK & more1088.45110
100%

Construction Progress

TOWER - B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station60%
✅Energy managemcnt
✅Fire protection and fire safety requirements70%
✅Internal Roads & Footpaths10%
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal
✅Storm Water Drains80%
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water75%
✅Water Supply
✅Water conservation /Rain water harvesting70%