Project Information

RERA Certificate No.
P51700019211
Registration No.
REA51700047838
Registration Date
2021-09-09
Developer
Regency Nirman Ltd Company
Architect
Vitan Consultants
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2022-05-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
13409.08 sq.m
Total FSI
11778.48
Approved FSI
11778.48
MahaRERA QR
Regency Sarvam Phase 11
MahaRERA — P51700019211
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors22
Sanctioned22
🏗️Proposed Floors22
Sanctioned22

Apartment Configurations

Building No 33

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.9615614313
92%

Building No 34

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.9615613521
87%

Construction Progress

Building No 33

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building No 34

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space100%
Community Buildings100%
Electrical meter room, sub-station, receiving station100%
Energy managemcnt100%
Fire protection and fire safety requirements100%
Internal Roads & Footpaths100%
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water100%
Water Supply100%
Water conservation /Rain water harvesting100%

Latest Mumbai Property News