Proposed Possession
2020-11-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Buildings
2
Project Area
4736.00 sq.m
Total FSI
3434.00
MahaRERA QR
Royale Seasons
MahaRERA — P99000010144
Scan to verify on MahaRERA portal

Wing-wise Details

⬇️Basements1
🅿️Closed Parking1
📅Completion1900-01-01
⬇️Basements1
🚗Open Parking10
📅Completion2020-12-31

Apartment Configurations

Royale Season 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
SHOP939.0404
0%

Royale Seasosns 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.8424204
83%
1RK21.7124168
67%

Construction Progress

Royale Season 2

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Royale Seasosns 1

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises20%
Overall Percentage of Completion of the work done For the entire Building /Wing33%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth80%
X number of Podiums80%
X number of Slabs of Super Structure50%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply1%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.