Rukmini Enclave
by Aditi Builders &Amp; Developers
Project Information
RERA Certificate No.
P99000021813
Registration No.
REA99000059135
Developer
Aditi Builders &Amp; Developers
Project Bank
BASSEIN CATHOLIC CO OP BANK LIMITED
Proposed Possession
2023-06-30
Revised Possession
1900-01-01
Extended Possession
2026-12-31
Buildings
2
Project Area
1528.36 sq.m
Total FSI
1528.36
Rukmini Enclave
MahaRERA — P99000021813
MahaRERA — P99000021813
Scan to verify on MahaRERA portal
Wing-wise Details
📅Completion2022-06-30
📅Completion2022-06-30
Apartment Configurations
Rukmini Enclave Building No 4 Wing C
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| FLAT | 18.27 | 1 | 1 | 0 | 100% |
| FLAT | 26.74 | 8 | 5 | 3 | 62% |
| FLAT | 28.03 | 2 | 2 | 0 | 100% |
| FLAT | 28.77 | 6 | 4 | 2 | 67% |
| FLAT | 31.03 | 1 | 1 | 0 | 100% |
| SHOP | 11.45 | 4 | 3 | 1 | 75% |
| SHOP | 12.81 | 2 | 2 | 0 | 100% |
Rukmini Enclave Building No 4 Wing D
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| FLAT | 18.27 | 1 | 1 | 0 | 100% |
| FLAT | 26.74 | 8 | 5 | 3 | 62% |
| FLAT | 26.77 | 6 | 4 | 2 | 67% |
| FLAT | 28.03 | 2 | 2 | 0 | 100% |
| FLAT | 31.03 | 1 | 1 | 0 | 100% |
| SHOP | 11.45 | 4 | 3 | 1 | 75% |
| SHOP | 12.81 | 2 | 1 | 1 | 50% |
Construction Progress
Rukmini Enclave Building No 4 Wing C
Rukmini Enclave Building No 4 Wing D
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station
⬜Energy management
⬜Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting
✅Water Supply