List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Ruparel Primero

by Shree Siddhivinayak Classic Construction Private Limited Company
Certificate SignedP51800021096
Ruparel PrimeroProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800021096
Registration No.
REA51800056792
Registration Date
2021-09-08
Developer
Shree Siddhivinayak Classic Construction Private Limited Company
Architect
Mr Rahul Kamathi
Project Bank
ICICI BANK LIMITED
Proposed Possession
2025-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
746.17 sq.m
Total FSI
3967.72
Approved FSI
2213.64
MahaRERA QR
Ruparel Primero
MahaRERA — P51800021096
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
✅Sanctioned20

Apartment Configurations

Ruaprel Primero

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.8215141
93%
1 BHK30.0117161
94%
1 BHK30.114122
86%
2 BHK62.2412102
83%

Construction Progress

Ruaprel Primero

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises82%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station50%
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)50%
✅Solid Waste Management And Disposal100%
✅Storm Water Drains50%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply50%
⬜Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now