List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Sadguru Nakshtra Phase I

by Sadguru Developers Partnership
Certificate SignedP51700017067
Sadguru Nakshtra Phase IProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700017067
Registration No.
REA51700040111
Registration Date
2021-09-09
Developer
Sadguru Developers Partnership
Architect
Dharmesh V Balani
Project Bank
HDFC BANK
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
6850.51 sq.m
Total FSI
9440.50
Approved FSI
5154.14
MahaRERA QR
Sadguru Nakshtra Phase I
MahaRERA — P51700017067
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors16
Sanctioned16
🏗️Proposed Floors16
Sanctioned16
🏗️Proposed Floors7
Sanctioned7

Apartment Configurations

B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.7514140
100%
1 BHK29.06660
100%
1 BHK29.0628280
100%
1 BHK29.09880
100%
2 BHK42.1614140
100%
2 BHK42.6214140
100%

C WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.3528280
100%
1 BHK29.4928280
100%
2 BHK43.4814140
100%

D WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.721257
42%
1 BHK33.79202
0%
1 BHK34.0112111
92%

Construction Progress

B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

C WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

D WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space100%
Community Buildings100%
Electrical meter room, sub-station, receiving station100%
Energy managemcnt
Fire protection and fire safety requirements100%
Internal Roads & Footpaths100%
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water
Water Supply100%
Water conservation /Rain water harvesting100%