List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Sai Vyankatesh

by Anjana Sahebrao Chavan Individual
Certificate SignedP51700016410
Sai VyankateshProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700016410
Registration No.
REA51700036765
Registration Date
2020-06-20
Developer
Anjana Sahebrao Chavan Individual
Architect
Architects Inn
Project Bank
BANK OF MAHARASHTRA
Proposed Possession
2021-06-30
Revised Possession
1900-01-01
Extended Possession
2022-03-30
Units Sold
0
Buildings
2
Project Area
1181.00 sq.m
Total FSI
1796.68
Approved FSI
1796.68
MahaRERA QR
Sai Vyankatesh
MahaRERA — P51700016410
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🏗️Proposed Floors9
Sanctioned9

Apartment Configurations

A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK41.62110
100%
1BHK43.2110
100%
1BHK44.41642
67%
2BHK58.62633
50%

B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK35.4110
100%
1BHK37.35660
100%
1BHK37.63110
100%
2BHK49.4213130
100%
2BHK56.39770
100%
3BHK58.5110
100%

Construction Progress

A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises90%
Slabs of Super Structure95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor100%

B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station10%
Energy managemcnt10%
Fire protection and fire safety requirements10%
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting25%