List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Sarkar Homes

by Sarkar Realty Partnership
Certificate SignedP99000019243
Sarkar HomesProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000019243
Registration No.
REA99000047692
Registration Date
2021-09-09
Developer
Sarkar Realty Partnership
Architect
Vasturachna Consultants
Project Bank
THE SHAMRAO VITHAL COOPERATIVE BANK
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
2108.43 sq.m
Total FSI
2384.73
Approved FSI
2384.73
MahaRERA QR
Sarkar Homes
MahaRERA — P99000019243
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors4
✅Sanctioned4
🏗️Proposed Floors4
✅Sanctioned4
🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

Building No-8 Type G

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK24.1321
67%
1BHK24.52651
83%
2BHK36.14330
100%
FLAT24.13303
0%
FLAT25.33312
33%
FLAT29.19101
0%
FLAT29.25101
0%
FLAT29.28101
0%
FLAT29.67202
0%
FLAT30.48101
0%

Building No-8 Type I

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK24.08624
33%
1RK16.62312
33%
FLAT21.62101
0%
FLAT23.49303
0%
FLAT26.39101
0%
FLAT29.22202
0%

Building No-8 Type K

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FLAT24.081275
58%
FLAT29.23404
0%
FLAT36.59431
75%

Construction Progress

Building No-8 Type G

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building No-8 Type I

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building No-8 Type K

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now