Sateri Legacy B Wing Phase I- 2Nd And Above Floors
by Bindra Sateri Constructions
Sateri Legacy B Wing Phase I- 2Nd And Above FloorsProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800024998
Registration No.
REA51800069973
Registration Date
2021-09-08
Developer
Bindra Sateri Constructions
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
211.69 sq.m
Total FSI
2058.89
Approved FSI
2033.91
Sateri Legacy B Wing Phase I- 2Nd And Above Floors
MahaRERA — P51800024998
MahaRERA — P51800024998
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors16
✅Sanctioned16
Apartment Configurations
Sateri Legacy B Wing Phase I- 2nd and above floors
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 34.02 | 39 | 0 | 39 | 0% |
| 1BHK | 34.12 | 12 | 0 | 12 | 0% |
| 1BHK | 49.55 | 1 | 0 | 1 | 0% |
| 1BHK | 49.65 | 1 | 0 | 1 | 0% |
Construction Progress
Sateri Legacy B Wing Phase I- 2nd and above floors
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting