List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Sauda Heights - Phase II

by MK India Enterprises
Certificate SignedP51900028008
Sauda Heights - Phase IIProject photos will appear here when available.

Project Information

RERA Certificate No.
P51900028008
Developer
MK India Enterprises
Architect
Amir Maredia Maredia
Project Bank
Union Bank of India
Proposed Possession
2027-10-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
150
Units Sold
44 (29%)
Buildings
2
Project Area
821.91 sq.m
Total FSI
12636.39
Approved FSI
5802.00
MahaRERA QR
Sauda Heights - Phase II
MahaRERA — P51900028008
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
✅Sanctioned24
🏠Habitable22
🔢Total Units90
🏡Residential80
🏢Non-Residential10
🏗️Proposed Floors24
✅Sanctioned24
🏠Habitable21
🔢Total Units60
🏡Residential60

Apartment Configurations

Tower II Rehab Wing - C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Shop24.99101
0%

Tower II Sale Wing - C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK40.6216511
31%
1BHK40.641459
36%
1BHK42.1220
100%
2BHK60.481367
46%
2BHK61.4214410
29%

Construction Progress

Tower II Rehab Wing - C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Tower II Sale Wing - C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station95%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal95%
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting95%

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now