Sayba Badr

by Star Shine Joint Venture
Certificate SignedPM1180002600563
Sayba BadrProject photos will appear here when available.

Project Information

RERA Certificate No.
PM1180002600563
Registration No.
PM1180002600563
Registration Date
2026-05-29
Developer
Star Shine Joint Venture
Proposed Possession
2029-10-30
Revised Possession
2029-06-30
Total Units
349
Units Sold
0 (0%)
Buildings
1
Project Area
19759.38 sq.m
MahaRERA QR
Sayba Badr
MahaRERA — PM1180002600563
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
🏠Habitable14
🔢Total Units67
🏡Residential63
🏢Non-Residential4
🏗️Proposed Floors15
Sanctioned15
🏠Habitable14
🔢Total Units56
🏡Residential51
🏢Non-Residential5
🏗️Proposed Floors14
Sanctioned14
🏠Habitable13
🔢Total Units55
🏡Residential47
🏢Non-Residential8
🏗️Proposed Floors14
Sanctioned14
🏠Habitable13
🔢Total Units52
🏡Residential47
🏢Non-Residential5
🏗️Proposed Floors14
Sanctioned14
🏠Habitable13
🔢Total Units52
🏡Residential47
🏢Non-Residential5
🏗️Proposed Floors14
Sanctioned14
🏠Habitable13
🔢Total Units67
🏡Residential59
🏢Non-Residential8

Construction Progress

Sayba Badr - A Wing

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Sayba Badr - B Wing

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Sayba Badr - C Wing

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Sayba Badr - D Wing

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Sayba Badr - E Wing

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Sayba Badr - F Wing

Basement (if any)75%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now