Seetai Co - Op. Hsg. Soc. Ltd. by Mahesh Parshuram Patil

Mahesh Parshuram Patil
πŸ“ Kalwa, Thane Β· 400605
β€”
Units
2029
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2029
Status
New
02

Unit Configurations (per MahaRERA)

03

RERA Trust Record

MahaRERA No.
P51700080363
Registered
2025-05-27
Litigation
None on record
Escrow Bank
IDBI BANK
Architect
Makrand Toraskar
Total FSI
1704
04

Buildings Β· 1 Wing(s)

SITAI CO OP HSG SOC LTD10 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Kalwa
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
09

Construction Progress

27% avg
Excavation100%
Stilt Floor 100%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by Mahesh Parshuram Patil

Chandrakiran Chs LtdKhar West Β· Sold Out
15

MahaRERA projects nearby in Kalwa

Maruti Homes162 unitsShree Sai Charan Chsl114 unitsRADHA KRISHNA PARK35 unitsJivdani BuildingSukur SublimeSUNSHINEBubera MansionShivanand Sra ChsJay Bharati Chs LtdOsho DayaramCHAVAN SARVESHWARAOjasvi Pinnacle
?

Frequently Asked Questions

When is possession of Seetai Co-Op. Hsg. Soc. Ltd.?

As per MahaRERA, proposed possession is Dec 2029.

Is Seetai Co-Op. Hsg. Soc. Ltd. RERA-registered?

Yes β€” MahaRERA registration P51700080363, registered 2025-05-27. No litigations on record.

Who is the developer?

Mahesh Parshuram Patil β€” 2 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Kalwa β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900006299β˜… Featured
Godrej Properties
Godrej Avenue Eleven B, Mahalaxmi
4 BHK Β· β‚Ή69,000/sq.ft Β· Possession Jan 2029
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’