📞 +91 98200 30685✉️
RERA: A51800043517

Seven Heights

by Aditi Builders And Developers
Kept in AbeyanceP99000047103

Project Information

RERA Certificate No.
P99000047103
Registration No.
REA99000106640
Developer
Aditi Builders And Developers
Project Bank
HDFC BANK
Proposed Possession
2025-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Buildings
3
Project Area
2484.29 sq.m
Total FSI
2484.29
MahaRERA QR
Seven Heights
MahaRERA — P99000047103
Scan to verify on MahaRERA portal

Wing-wise Details

📅Completion2025-12-31
📅Completion2025-12-31
📅Completion2025-12-31

Apartment Configurations

Seven Heights Buld No 2, A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.7214014
0%
1 BHK29.96202
0%
Shop9.94101
0%
Shop10.7202
0%
Shop13.65303
0%

Seven Heights Buld No2, B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.76606
0%
1 BHK30.83808
0%
1 BHK31.64101
0%
1 BHK32.07101
0%
1 BHK32.22303
0%
1 BHK32.8101
0%
2 BHK43.96303
0%
2 BHK44.88101
0%
Shop11.39101
0%
Shop11.6101
0%
Shop13.19101
0%
Shop13.27101
0%
Shop14.22101
0%
Shop14.48404
0%
Shop14.75101
0%
Shop16.43101
0%
Shop16.95101
0%
Shop19.01101
0%

Seven Heights, Buld No 2, C Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.7214014
0%
1 BHK29.96202
0%
Shop9.94101
0%
Shop10.7202
0%
Shop13.65303
0%

Construction Progress

Seven Heights Buld No 2, A Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Seven Heights Buld No2, B Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing15%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth50%
X number of Podiums0%
X number of Slabs of Super Structure0%

Seven Heights, Buld No 2, C Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now