RERA: A51800043517

SHAMBHAVI APARTMENTS

by JAYESH BALVANT JANI Individual
Certificate SignedP99000051399

Project Information

RERA Certificate No.
P99000051399
Registration No.
REA99000135555
Registration Date
2023-06-08
Developer
JAYESH BALVANT JANI Individual
Architect
Nandadeep Kokane
Project Bank
ICICI BANK LIMITED
Proposed Possession
2028-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
42
Units Sold
18 (43%)
Buildings
3
Project Area
1929.69 sq.m
Total FSI
1927.70
Approved FSI
1927.70
MahaRERA QR
SHAMBHAVI APARTMENTS
MahaRERA — P99000051399
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors4
Sanctioned4
🏠Habitable4
🔢Total Units27
🏡Residential27
🅿️Closed Parking1
📅Completion2028-12-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units6
🏡Residential6
📅Completion2028-12-30
🏗️Proposed Floors4
Sanctioned4
🏠Habitable4
🔢Total Units9
🏡Residential9
🅿️Closed Parking1
📅Completion2028-12-30

Apartment Configurations

Type -D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.0312012
0%
1 BHK36.23303
0%
1 BHK37.09303
0%
2 BHK49.13606
0%
2 BHK54.2303
0%

Type -G

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.61202
0%
1 BHK39.3404
0%

Type E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.74606
0%
1 BHK38.59303
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk34.7400016784668000
0%
1Bhk36.029998779296875000
0%
1Bhk36.22999954223633000
0%
1Bhk36.61000061035156000
0%
1Bhk37.09000015258789000
0%
1Bhk38.59000015258789000
0%
1Bhk39.29999923706055000
0%
2Bhk49.130001068115234000
0%
2Bhk54.20000076293945000
0%

Construction Progress

Type -D

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Type -G

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing28%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure80%

Type E

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75%
Overall Percentage of Completion of the work done For the entire Building /Wing61%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now