Shiv Parvati Complex
by Linkpromoters &Amp; Pokar Enterprises
Shiv Parvati ComplexProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800005290
Registration No.
REA51800015230
Developer
Linkpromoters &Amp; Pokar Enterprises
Project Bank
UNITED BANK OF INDIA
Proposed Possession
2019-03-31
Revised Possession
2019-03-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
3831.20 sq.m
Total FSI
4557.96
Approved FSI
6.71
Shiv Parvati Complex
MahaRERA — P51800005290
MahaRERA — P51800005290
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors9
✅Sanctioned9
Apartment Configurations
SHIV PARVATI COMPLEX
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 37.07 | 26 | 25 | 1 | 96% |
| 1 BHK | 43.48 | 12 | 10 | 2 | 83% |
| 1 BHK | 43.75 | 2 | 0 | 2 | 0% |
| 1BHK | 36.51 | 12 | 12 | 0 | 100% |
| 2BHK | 55.09 | 33 | 28 | 5 | 85% |
| SHOP | 10.03 | 1 | 0 | 1 | 0% |
| SHOP | 10.13 | 1 | 0 | 1 | 0% |
| SHOP | 10.87 | 1 | 0 | 1 | 0% |
| SHOP | 12.36 | 1 | 0 | 1 | 0% |
| SHOP | 13.38 | 1 | 0 | 1 | 0% |
| SHOP | 13.47 | 1 | 0 | 1 | 0% |
| SHOP | 13.56 | 1 | 0 | 1 | 0% |
| SHOP | 13.84 | 1 | 0 | 1 | 0% |
| SHOP | 14.49 | 1 | 0 | 1 | 0% |
| SHOP | 14.59 | 1 | 0 | 1 | 0% |
| SHOP | 15.14 | 1 | 0 | 1 | 0% |
| SHOP | 15.51 | 1 | 0 | 1 | 0% |
| SHOP | 15.7 | 1 | 0 | 1 | 0% |
| SHOP | 17.09 | 1 | 0 | 1 | 0% |
| SHOP | 18.21 | 1 | 0 | 1 | 0% |
| SHOP | 19.32 | 2 | 0 | 2 | 0% |
| SHOP | 19.6 | 1 | 0 | 1 | 0% |
| SHOP | 19.7 | 1 | 0 | 1 | 0% |
| SHOP | 20.25 | 1 | 0 | 1 | 0% |
| SHOP | 26.38 | 1 | 0 | 1 | 0% |
| SHOP | 73.67 | 1 | 0 | 1 | 0% |
Construction Progress
SHIV PARVATI COMPLEX
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station70%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting60%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)80%
✅Solid Waste Management And Disposal50%
✅Storm Water Drains50%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply40%