List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Shraddha Autumn Park

by Atharva Developers Partnership
Certificate SignedP51800007651
Shraddha Autumn ParkProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800007651
Registration No.
REA51800018038
Registration Date
2021-09-10
Developer
Atharva Developers Partnership
Project Bank
IDBI BANK
Proposed Possession
2028-04-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
3850.00 sq.m
Total FSI
7139.74
Approved FSI
5738.78
MahaRERA QR
Shraddha Autumn Park
MahaRERA — P51800007651
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
✅Sanctioned25
🏗️Proposed Floors25
✅Sanctioned25
🏗️Proposed Floors25
✅Sanctioned25
🏗️Proposed Floors24
✅Sanctioned24
🏗️Proposed Floors25
✅Sanctioned25

Apartment Configurations

BUILDING NO 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK34.2822211
95%
1BHK34.8419190
100%
1BHK37.3523221
96%
2BHK45.1521210
100%
2BHK46.45110
100%
2BHK56.39110
100%

BUILDING NO 2 WING A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.6422220
100%
1BHK34.4723221
96%
1BHK34.6522220
100%

BUILDING NO 2 WING B REHAB

TypeCarpet (sq.ft)TotalBookedAvailableStatus
NA—000
0%

BUILDING NO 3 WING A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK27.96927
22%
1BHK30.19918
11%

BUILDING NO 3 WING B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK25.2712012
0%
1BHK25.5512012
0%
1RK15.89101
0%

Construction Progress

BUILDING NO 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 2 WING A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 2 WING B REHAB

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 3 WING A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 3 WING B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station80%
⬜Energy managemcnt
✅Fire protection and fire safety requirements66%
✅Internal Roads & Footpaths75%
✅Landscaping & Tree Planting60%
✅OTHER FITNESS CENTER100%
✅OTHER SOCIETY OFFICE100%
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)75%
⬜Solid Waste Management And Disposal
✅Storm Water Drains66%
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply66%
✅Water conservation /Rain water harvesting50%