List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Shree Parshwanath Sra Chs Ltd

by Chintamani Realtors
Certificate SignedP51800009968
Shree Parshwanath Sra Chs LtdProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800009968
Registration No.
REA51800013124
Developer
Chintamani Realtors
Project Bank
DNS BANK
Proposed Possession
2024-03-31
Revised Possession
1900-01-01
Extended Possession
2024-03-31
Units Sold
0
Buildings
3
Project Area
2126.00 sq.m
Total FSI
8408.37
MahaRERA QR
Shree Parshwanath Sra Chs Ltd
MahaRERA — P51800009968
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors19
✅Sanctioned19
🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors25
✅Sanctioned25

Apartment Configurations

Rehab wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK33.4611110
100%

Rehab wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Shop4.65110
100%
Shop5.95110
100%
Shop9.29110
100%

Sale wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK31.6101
0%
1BHK39.2218180
100%
1BHK39.4116151
94%
2BHK58.3618108
56%
2BHK61.1518144
78%
Shop19.7110
100%

Construction Progress

Rehab wing B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Rehab wing C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Sale wing A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements98%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting90%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting