List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Shreeji Meadows

by Deeplaxmi Developers Partnership
Certificate SignedP51700031453
Shreeji MeadowsProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700031453
Registration No.
REA51700095820
Registration Date
2021-10-23
Developer
Deeplaxmi Developers Partnership
Architect
URBAN VASTU DESIGNER
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2026-07-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
400
Units Sold
266 (66%)
Buildings
3
Project Area
6610.00 sq.m
Total FSI
19897.31
Approved FSI
19897.31
MahaRERA QR
Shreeji Meadows
MahaRERA — P51700031453
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors13
✅Sanctioned13
🏠Habitable13
🔢Total Units136
🏡Residential132
🏢Non-Residential4
🏗️Proposed Floors13
✅Sanctioned13
🏠Habitable13
🔢Total Units132
🏡Residential132
🏗️Proposed Floors13
✅Sanctioned13
🏠Habitable13
🔢Total Units132
🏡Residential132

Apartment Configurations

BUILDING 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.45867511
87%
1RK19.11220
100%
2BHK44.7744431
98%
Shop16.12101
0%
Shop22.84101
0%
Shop23.21101
0%
Shop24.17101
0%

BUILDING 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.45861472
16%
1RK19.11211
50%
2BHK44.77441232
27%

BUILDING 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.4586086
0%
1RK19.11202
0%
2BHK44.7744044
0%

Construction Progress

BUILDING 1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 2

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 3

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space100%
✅Community Buildings100%
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%