RERA: A51800043517

Shri Gana Siddhivinayak Sra Chs Ltd

by Gharandaj Builders
Kept in AbeyanceP51900012725
šŸ’¬ WhatsAppšŸ“ž Call

Project Information

RERA Certificate No.
P51900012725
Registration No.
REA51900020467
Developer
Gharandaj Builders
Project Bank
Union Bank Ltd
Proposed Possession
2001-03-31
Revised Possession
2022-03-30
Extended Possession
1900-01-01
Buildings
3
Project Area
5528.77 sq.m
Total FSI
13814.96
Approved FSI
6444.00
Litigations
āš ļø Yes
MahaRERA QR
Shri Gana Siddhivinayak Sra Chs Ltd
MahaRERA — P51900012725
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ“…Completion1900-01-01
šŸ“…Completion1900-01-01
šŸš—Open Parking26
šŸ…æļøClosed Parking1
šŸ“…Completion1900-01-01

Apartment Configurations

Composite 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK20.91220
100%

Composite 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK20.91000
0%

Yashowan

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK57.151417-3
121%
2.5 BHK63.01417-3
121%
3 BHK82.091217-5
142%

Construction Progress

Composite 1

Excavation50%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%
Overall Percentage of Completion of the work done For the entire Building /Wing40%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth50%
X number of Podiums0%
X number of Slabs of Super Structure50%

Composite 2

Excavation50%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%
Overall Percentage of Completion of the work done For the entire Building /Wing40%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth50%
X number of Podiums0%
X number of Slabs of Super Structure50%

Yashowan

Excavation50%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate25%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor25%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth50%
X number of Podiums25%
X number of Slabs of Super Structure100%

RERA Registered Amenities

āœ…Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station100%
⬜Energy management
āœ…Fire Protection And Fire Safety Requirements27%
āœ…Landscaping & Tree Planting
āœ…Open Parking27%
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
⬜Water Conservation, Rain water Harvesting
āœ…Water Supply27%
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.