SHRIPAL SHANTI PHASE - 1
by SHRIPAL SHANTI LLP
Partnership
Project Information
RERA Certificate No.
P99000027903
Registration No.
REA99000083170
Registration Date
2021-09-08
Developer
SHRIPAL SHANTI LLP Partnership
Project Bank
INDUSIND BANK
Proposed Possession
2025-03-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
2523.91 sq.m
Total FSI
9104.36
Approved FSI
9104.36
SHRIPAL SHANTI PHASE - 1
MahaRERA — P99000027903
MahaRERA — P99000027903
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors25
✅Sanctioned25
🅿️Closed Parking91
📅Completion2024-09-30
Apartment Configurations
Shripal Shanti Tower 1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 36.66 | 92 | 80 | 12 | 87% |
| 1 BHK | 38.16 | 22 | 16 | 6 | 73% |
| 2 BHK | 47.5 | 23 | 21 | 2 | 91% |
| 2 BHK | 48.14 | 65 | 57 | 8 | 88% |
Construction Progress
SHRIPAL SHANTI TOWER 1
Shripal Shanti Tower 1
RERA Registered Amenities
✅Aggregate area of recreational Open Space100%
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station100%
⬜Energy management
✅Fire Protection And Fire Safety
Requirements100%
✅Landscaping & Tree Planting100%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal100%
✅Storm Water Drains100%
✅Street Lighting100%
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Conservation, Rain water Harvesting100%
✅Water Supply100%