List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

SIDDHIVINAYAK RIDDHIMA

by SIDDHIVINAYAK HOMES Partnership
Certificate SignedP52000018157
SIDDHIVINAYAK RIDDHIMAProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000018157
Registration No.
REA52000045168
Registration Date
2021-09-09
Developer
SIDDHIVINAYAK HOMES Partnership
Architect
Adinath Patkar
Project Bank
PUNJAB NATIONAL BANK
Proposed Possession
2024-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
7
Project Area
10055.00 sq.m
Total FSI
30035.79
Approved FSI
10035.79
MahaRERA QR
SIDDHIVINAYAK RIDDHIMA
MahaRERA — P52000018157
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6

Apartment Configurations

BUILDING NO 1, A, B and C Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential29.63880
100%
Residential30.7880
100%
Residential31.46651
83%
Residential31.5232311
97%

BUILDING NO 2, D Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential29.63440
100%
Residential30.13220
100%
Residential30.62220
100%
Residential30.66220
100%
Residential30.7660
100%
Residential30.77202
0%
Residential30.78211
50%
Residential31.15220
100%
Residential31.231293
75%
Residential31.46220
100%

BUILDING NO 3, E Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential30.716160
100%
Residential31.15220
100%
Residential31.2316142
88%
Residential31.46220
100%

BUILDING NO 4, F Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential30.71248
33%
Residential30.75422
50%
Residential31.46220
100%

BUILDING NO 5, G, H and I Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Commercial9.63550
100%
Commercial12.92550
100%
Residential29.63880
100%
Residential30.7880
100%
Residential31.46660
100%
Residential31.5232320
100%

BUILDING NO 6, J and K Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential45.132320
100%

BUILDING NO 7, L and M Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential45.132320
100%

Construction Progress

BUILDING NO 1, A, B and C Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 2, D Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 3, E Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 4, F Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 5, G, H and I Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 6, J and K Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 7, L and M Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space100%
✅Community Buildings100%
⬜Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting100%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
⬜Water conservation /Rain water harvesting