📞 +91 98200 30685✉️
RERA: A51800043517

signature heights

by suraj dinesh singh
Kept in AbeyanceP99000025366

Project Information

RERA Certificate No.
P99000025366
Developer
suraj dinesh singh
Architect
Devendra Mistry Architect And Interior Designer
Project Bank
Vasai Vikas Sahkari Bank LTD
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
2025-12-31
Buildings
3
Project Area
3378.00 sq.m
Total FSI
1809.96
MahaRERA QR
signature heights
MahaRERA — P99000025366
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking24
📅Completion2023-03-31
🚗Open Parking62
🅿️Closed Parking62
📅Completion2023-03-31
🚗Open Parking1
🅿️Closed Parking1
📅Completion2023-03-31

Apartment Configurations

Signature Heights Bldg 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.15220
100%
1 BHK35.66211
50%
1 BHK38.88110
100%
2 BHK60.76110
100%
Shop13.47211
50%
Shop14.57211
50%
Shop16.22312
33%

Signature Hieghts Bldg 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.48110
100%
1 BHK36.51330
100%
1 BHK37.63110
100%
2 BHK59.93422
50%
2 BHK60.11312
33%
2 BHK60.31312
33%
ALLOTTED TOLANDOWNER37.63220
100%
Allotted toLandowner36.48220
100%
Allotted toLandowner59.93220
100%
Shop13.84211
50%
Shop14.67220
100%
Shop17.42220
100%
Shop17.671037
30%

Signature Villas

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Allotted toLandowner73.12110
100%
Bungalow73.17101
0%

Construction Progress

Signature Heights Bldg 2

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor73%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

Signature Hieghts Bldg 1

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing38%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure80%

Signature Villas

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%
Overall Percentage of Completion of the work done For the entire Building /Wing48%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now