Silver SpringsProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800009204
Registration No.
REA51800008447
Registration Date
2021-09-09
Developer
Shrikrishna Developers Partnership
Project Bank
THE COSMOS CO OPERATIVE BANK LIMITED
Proposed Possession
2027-12-31
Revised Possession
2021-12-30
Extended Possession
2024-12-31
Units Sold
0
Buildings
1
Project Area
1922.10 sq.m
Total FSI
4887.12
Approved FSI
4287.09
Silver Springs
MahaRERA — P51800009204
MahaRERA — P51800009204
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors13
✅Sanctioned13
Apartment Configurations
Silver Springs
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 38.52 | 12 | 9 | 3 | 75% |
| 1BHK | 45.88 | 12 | 4 | 8 | 33% |
| 1BHK | 50.46 | 12 | 8 | 4 | 67% |
| 2BHK | 59.41 | 12 | 3 | 9 | 25% |
| 2BHK | 59.56 | 12 | 4 | 8 | 33% |
| 2BHK | 64.99 | 11 | 3 | 8 | 27% |
| Shop | 5.73 | 1 | 0 | 1 | 0% |
| Shop | 6.39 | 1 | 0 | 1 | 0% |
| Shop | 10.33 | 1 | 0 | 1 | 0% |
| Shop | 21.7 | 1 | 0 | 1 | 0% |
Construction Progress
Silver Springs
RERA Registered Amenities
✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station80%
⬜Energy managemcnt
✅Fire protection and fire safety requirements90%
✅Garden Parking Camera installation fabrication etc50%
✅Internal Roads & Footpaths80%
✅Landscaping & Tree Planting50%
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)90%
✅Solid Waste Management And Disposal80%
✅Storm Water Drains90%
✅Street Lighting10%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting50%