List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Simran Heights

by Vikas Narayan Raikar Individual
Certificate SignedP51800002238
Simran HeightsProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800002238
Registration No.
REA51800008041
Registration Date
2017-07-31
Developer
Vikas Narayan Raikar Individual
Architect
S V Chemburkar
Project Bank
BANK OF BARODA
Proposed Possession
2025-03-31
Revised Possession
2019-09-24
Extended Possession
2025-03-31
Units Sold
0
Buildings
2
Project Area
4866.72 sq.m
Total FSI
6444.33
Approved FSI
3393.98
MahaRERA QR
Simran Heights
MahaRERA — P51800002238
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23

Apartment Configurations

Simran Heights - Phase I

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK44.44880
100%
1 BHK45.43770
100%
1 BHK51.39880
100%
2 BHK62.29770
100%
2 BHK62.51880
100%
2 BHK63.91880
100%
3 BHK72.59110
100%

Simran Heights - Phase Ii

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK44.4418180
100%
1 BHK45.4310100
100%
1 BHK51.3913130
100%
2 BHK62.29990
100%
2 BHK62.5113130
100%
2 BHK63.9113130
100%

Construction Progress

SIMRAN HEIGHTS - PHASE I

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor100%

SIMRAN HEIGHTS - Phase II

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space100%
Community Buildings100%
Electrical meter room, sub-station, receiving station100%
Energy managemcnt100%
Fire protection and fire safety requirements100%
Internal Roads & Footpaths
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting100%