📞 +91 98200 30685 ✉️
RERA: A51800043517

S.K. HEIGHTS

by NINE REALCON INFRA PRIVATE LIMITED Company
Certificate Signed P99000034701
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P99000034701
Registration No.
REA99000105557
Registration Date
2024-05-31
Developer
NINE REALCON INFRA PRIVATE LIMITED Company
Architect
Ar Ashok Krishna Rengde
Project Bank
HDFC BANK
Proposed Possession
2027-03-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
2697.47 sq.m
Total FSI
10810.35
Approved FSI
10492.18
MahaRERA QR
S.K. HEIGHTS
MahaRERA — P99000034701
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
🚗Open Parking20
🅿️Closed Parking20
📅Completion2027-03-31
📅Completion2027-03-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 28.700000762939453 0 0 0
0%
1Bhk 29.010000228881836 0 0 0
0%
1Bhk 29.030000686645508 0 0 0
0%
1Bhk 35.18000030517578 0 0 0
0%
2Bhk 45.58000183105469 0 0 0
0%
2Bhk 45.970001220703125 0 0 0
0%
2Bhk 46.61000061035156 0 0 0
0%
2Bhk 47.36000061035156 0 0 0
0%
Shop 27.040000915527344 0 0 0
0%
Shop 37.16999816894531 0 0 0
0%
Shop 38.84000015258789 0 0 0
0%
Shop 39.349998474121094 0 0 0
0%
Shop 39.47999954223633 0 0 0
0%

S K Heights

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.7 22 15 7
68%
1 BHK 29.01 22 13 9
59%
1 BHK 29.03 22 13 9
59%
1 BHK 35.18 3 1 2
33%
2 BHK 45.58 21 10 11
48%
2 BHK 45.97 21 16 5
76%
2 BHK 46.61 18 15 3
83%
2 BHK 47.36 21 18 3
86%
Shop 27.04 1 1 0
100%
Shop 37.17 1 1 0
100%
Shop 38.84 1 1 0
100%
Shop 39.35 1 0 1
0%
Shop 39.48 1 0 1
0%

S K Heihgts Prposed

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.7 1 0 1
0%
1 BHK 29.01 1 0 1
0%
1 BHK 29.03 1 0 1
0%
2 BHK 45.58 1 0 1
0%
2 BHK 45.97 1 0 1
0%
2 BHK 46.61 1 0 1
0%
2 BHK 47.36 1 0 1
0%

Construction Progress

S K HEIGHTS

Basement (if any)100%

S K Heights

Excavation100%

S K HEIGHTS

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

S K Heights

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%

S K HEIGHTS

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%

S K Heights

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises15%
Overall Percentage of Completion of the work done For the entire Building /Wing43%

S K HEIGHTS

Plinth100%
Podiums (if any) 0%

S K Heights

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

S K HEIGHTS

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure60%

S K Heights

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.35%

S K HEIGHTS

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%

S K Heights

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure60%

S K HEIHGTS PRPOSED

Basement (if any)0%

S K Heihgts Prposed

Excavation0%

S K HEIHGTS PRPOSED

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

S K Heihgts Prposed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

S K HEIHGTS PRPOSED

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

S K Heihgts Prposed

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

S K HEIHGTS PRPOSED

Plinth0%
Podiums (if any) 0%

S K Heihgts Prposed

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

S K HEIHGTS PRPOSED

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

S K Heihgts Prposed

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

S K HEIHGTS PRPOSED

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

S K Heihgts Prposed

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.