Sky Residency Loksadan Chs Phase 1 Up To G Plus 7Pt.
by Sky Property Developers Private Limited
Sky Residency Loksadan Chs Phase 1 Up To G Plus 7Pt.Project photos will appear here when available.
Project Information
RERA Certificate No.
P51800003387
Registration No.
REA51800012786
Registration Date
2017-12-07
Developer
Sky Property Developers Private Limited
Architect
Tangent Design And Cell
Project Bank
ICICI BANK LIMITED
Proposed Possession
2017-12-31
Revised Possession
2017-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
450.00 sq.m
Total FSI
1200.55
Approved FSI
1200.55
Sky Residency Loksadan Chs Phase 1 Up To G Plus 7Pt.
MahaRERA — P51800003387
MahaRERA — P51800003387
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors9
✅Sanctioned9
Apartment Configurations
Sky Residency Loksadan CHS Phase 1 Up to G Plus 7p
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 38.7 | 3 | 3 | 0 | 100% |
| 1BHK | 43.95 | 3 | 3 | 0 | 100% |
| 2BHK | 47.49 | 1 | 1 | 0 | 100% |
| 2BHK | 51.59 | 2 | 2 | 0 | 100% |
| 2BHK | 53.72 | 3 | 3 | 0 | 100% |
| 2BHK | 55.25 | 3 | 3 | 0 | 100% |
| 2BHK | 55.62 | 1 | 1 | 0 | 100% |
| 2BHK | 58.53 | 3 | 3 | 0 | 100% |
| Shop | 15.99 | 1 | 1 | 0 | 100% |
| shop | 11.85 | 1 | 1 | 0 | 100% |
| shop | 22.18 | 1 | 1 | 0 | 100% |
| shop | 22.58 | 1 | 1 | 0 | 100% |
| shop | 27.77 | 1 | 1 | 0 | 100% |
Construction Progress
Sky Residency Loksadan CHS Phase 1 Up to G Plus 7p
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply80%
⬜Water conservation /Rain water harvesting