List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Skyline Wing - C

by Shri Ratnaraj Infra Llp Partnership
Certificate SignedP51700050558
Skyline Wing - CProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700050558
Registration No.
REA51700134375
Registration Date
2023-04-21
Developer
Shri Ratnaraj Infra Llp Partnership
Architect
MARIO E CORREA
Project Bank
HDFC BANK
Proposed Possession
2029-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
255
Units Sold
128 (50%)
Buildings
1
Project Area
11177.78 sq.m
Total FSI
21405.91
Approved FSI
21405.91
MahaRERA QR
Skyline Wing - C
MahaRERA — P51700050558
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors38
✅Sanctioned38
🏠Habitable35
🔢Total Units255
🏡Residential255

Apartment Configurations

SKYLINE WING C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK42.25633924
62%
2BHK62.25623923
63%
2BHK66.05602238
37%
2BHK67.75702248
31%

Construction Progress

SKYLINE WING C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting