Project Information

RERA Certificate No.
P51800013435
Registration No.
REA51800023780
Developer
Qureshi Builders
Project Bank
ORIENTAL BANK OF COMMERCE
Proposed Possession
2023-12-30
Revised Possession
2023-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
1567.00 sq.m
Total FSI
2745.00
Approved FSI
245.00
MahaRERA QR
Skyper
MahaRERA — P51800013435
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
✅Sanctioned20
🏗️Proposed Floors2
✅Sanctioned2
🏗️Proposed Floors17
✅Sanctioned17

Apartment Configurations

SKYPER

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK41.45330
100%
4BHK155.02220
100%
4BHK160.78110
100%
4BHK162.6412111
8%

SKYPER B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
MARKET384.0110
100%

SKYPER C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL1035.030030
0%

Construction Progress

SKYPER

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Plinth100%
Podiums (if any)2%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure19%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor1%

SKYPER B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
Stilt Floor100%

SKYPER C

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space100%
✅Community Buildings10%
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt80%
✅Fire protection and fire safety requirements95%
⬜Internal Roads & Footpaths
✅LIFT STAIRCASE TERRACE70%
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal60%
✅Storm Water Drains100%
⬜Street Lighting10%
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply70%
✅Water conservation /Rain water harvesting10%

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now