List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

SUKH SHANTI NAGAR

by EKNATH APPARAO PARJANE
Certificate SignedP52000045270
SUKH SHANTI NAGARProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000045270
Developer
EKNATH APPARAO PARJANE
Architect
M/S. Hexagon Project Consultant
Project Bank
BANK OF BARODA
Proposed Possession
2027-04-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
176
Units Sold
94 (53%)
Buildings
5
Project Area
4300.00 sq.m
Total FSI
7429.74
MahaRERA QR
SUKH SHANTI NAGAR
MahaRERA — P52000045270
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
✅Sanctioned3
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units51
🏡Residential44
🏢Non-Residential7
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units45
🏡Residential28
🏢Non-Residential17
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units36
🏡Residential36
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units44
🏡Residential44

Apartment Configurations

1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK20.020020
0%

2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK33.033033
0%
2BHK52.011011
0%
Shop20.0707
0%

3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK31.012012
0%
1RK20.0404
0%
2BHK55.012012
0%
Shop10.116016
0%

4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK31.016016
0%
1RK21.012012
0%
2BHK49.0808
0%

5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK35.044044
0%

Construction Progress

1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

2

Basement (if any)10%
Excavation15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth10%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor5%

3

Basement (if any)5%
Excavation10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth5%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

4

Basement (if any)0%
Excavation10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

5

Basement (if any)10%
Excavation15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth10%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space10%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station10%
⬜Energy managemcnt
✅Fire protection and fire safety requirements10%
✅Internal Roads & Footpaths10%
✅Landscaping & Tree Planting
✅Open Parking20%
✅Sewerage (Chamber, Lines, Septic Tank , STP)10%
✅Solid Waste Management And Disposal15%
⬜Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply10%
✅Water conservation /Rain water harvesting10%