SUNRAJ SOLITAIRE

by Sunraj Construction Others
Certificate SignedP51700077991
SUNRAJ SOLITAIREProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700077991
Registration No.
REA51700165025
Registration Date
2024-11-14
Developer
Sunraj Construction Others
Architect
Rachana Shilp Architect & Interior Designers
Project Bank
UNION BANK OF INDIA
Proposed Possession
2032-04-30
Total Units
328
Units Sold
105 (32%)
Buildings
3
Project Area
11032.75 sq.m
Total FSI
50594.67
Approved FSI
23366.98
MahaRERA QR
SUNRAJ SOLITAIRE
MahaRERA — P51700077991
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors26
✅Sanctioned24
🏠Habitable23
🔢Total Units239
🏡Residential239
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable5
🔢Total Units48
🏡Residential48
🏗️Proposed Floors4
✅Sanctioned4
🏠Habitable4
🔢Total Units41
🏡Residential10
🏢Non-Residential31

Apartment Configurations

Building No- 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.061640164
0%
1 BHK MHADA41.0612012
0%
2 BHK56.0242042
0%
2 BHK60.7621021
0%

Building No-2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.0624024
0%
1 BHK MHADA41.0618018
0%
2 BHK56.02606
0%

Building No-3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.06202
0%
1 BHK T41.06606
0%
2 BHK56.02202
0%
Office space20.6212012
0%
Office space21.09101
0%
Office space42.18202
0%
Shop20.5316016
0%

Construction Progress

Building No- 1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure54%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%

Building No-2

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No-3

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting