SWAPNALOK RESIDENCY PHASE II
by ASHAPURA BUILDERS & DEVELOPERS
Partnership
Project Information
RERA Certificate No.
P99000015658
Registration No.
REA99000032925
Registration Date
2018-03-15
Developer
ASHAPURA BUILDERS & DEVELOPERS Partnership
Architect
Vastu Shilp
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2018-12-31
Revised Possession
1900-01-01
Extended Possession
2024-12-30
Units Sold
0
Buildings
1
Project Area
5000.00 sq.m
Total FSI
476.15
Approved FSI
476.15
SWAPNALOK RESIDENCY PHASE II
MahaRERA — P99000015658
MahaRERA — P99000015658
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors11
✅Sanctioned11
🚗Open
Parking10
🅿️Closed Parking8
📅Completion2018-12-31
Apartment Configurations
Riddhi A Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 142.01 | 4 | 2 | 2 | 50% |
| 2 BHK | 213.01 | 4 | 0 | 4 | 0% |
| Shop | 74.23 | 6 | 1 | 5 | 17% |
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 142.00999450683594 | 0 | 0 | 0 | 0% |
| 2Bhk | 213.00999450683594 | 0 | 0 | 0 | 0% |
| Shop | 74.2300033569336 | 0 | 0 | 0 | 0% |
Construction Progress
RIDDHI A WING
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station100%
⬜Energy management
⬜Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting100%
✅Water Supply100%