SYMPHONY IProject photos will appear here when available.
Project Information
RERA Certificate No.
P52000021220
Registration No.
REA52000057391
Registration Date
2021-09-08
Developer
K AND S INFRA Partnership
Architect
Triarch Design Studio
Project Bank
AXIS BANK
Proposed Possession
2023-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
399.76 sq.m
Total FSI
599.50
Approved FSI
599.50
SYMPHONY I
MahaRERA — P52000021220
MahaRERA — P52000021220
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors6
✅Sanctioned6
Apartment Configurations
SYMPHONY I
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 24.26 | 3 | 2 | 1 | 67% |
| 1 BHK | 25.25 | 1 | 0 | 1 | 0% |
| 1 BHK | 25.67 | 6 | 2 | 4 | 33% |
| 1 BHK | 28.06 | 3 | 2 | 1 | 67% |
| 1 BHK | 29.46 | 3 | 1 | 2 | 33% |
| 1 RK WITH TERRACE | 17.44 | 1 | 0 | 1 | 0% |
| 1 RK WITH TERRACE | 19.37 | 1 | 0 | 1 | 0% |
| 1 RK WITH TERRACE | 19.37 | 1 | 1 | 0 | 100% |
| 1 RK WITH TERRACE | 21.61 | 1 | 1 | 0 | 100% |
| SHOP NO 1 | 9.31 | 1 | 0 | 1 | 0% |
| SHOP NO 2 | 10.82 | 1 | 0 | 1 | 0% |
| SHOP NO 3 | 14.01 | 1 | 0 | 1 | 0% |
| SHOP NO 4 | 13.79 | 1 | 0 | 1 | 0% |
Construction Progress
SYMPHONY I
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station20%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting50%