List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

The Palms

by Tanishq Builders Partnership
Certificate SignedP51800003688
The PalmsProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800003688
Registration No.
REA51800010706
Registration Date
2023-07-27
Developer
Tanishq Builders Partnership
Architect
ASHISH BHATT
Project Bank
HDFC BANK
Proposed Possession
2025-12-31
Revised Possession
2021-06-30
Extended Possession
2025-12-31
Units Sold
0
Buildings
5
Project Area
7806.72 sq.m
Total FSI
26345.00
Approved FSI
15937.66
MahaRERA QR
The Palms
MahaRERA — P51800003688
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors18
✅Sanctioned18
🏗️Proposed Floors18
✅Sanctioned18
🏗️Proposed Floors18
✅Sanctioned18
🏗️Proposed Floors18
✅Sanctioned18
🏗️Proposed Floors18
✅Sanctioned18

Apartment Configurations

THE PALMS - WIND D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK78.3815411
27%
2BHK79.02251114
44%
2BHK79.921367
46%

THE PALMS - WING B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK93.7517143
82%

THE PALMS - WING C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK79.02281612
57%
2BHK79.85281414
50%

THE PALMS - WING E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK117.030822
27%

THE PALMS WING A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK59.491138
27%
2BHK79.871459
36%
4BHK151.8112111
92%

Construction Progress

THE PALMS - WIND D

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

THE PALMS - WING B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor80%

THE PALMS - WING C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor80%

THE PALMS - WING E

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

THE PALMS WING A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor80%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting