The Royal TuskProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800004265
Registration No.
REA51800011739
Registration Date
2021-09-09
Developer
Soham Mahavir Developers Others
Architect
Vinod B Karwa
Project Bank
THE COSMOS CO OPERATIVE BANK LIMITED
Proposed Possession
2024-12-30
Revised Possession
2024-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1337.80 sq.m
Total FSI
5306.85
Approved FSI
5306.85
The Royal Tusk
MahaRERA — P51800004265
MahaRERA — P51800004265
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors21
✅Sanctioned21
Apartment Configurations
THE ROYAL TUSK
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| REHAB RESIDENTIAL | 2016.51 | 52 | 51 | 1 | 98% |
| REHAB SHOPS | 469.13 | 23 | 23 | 0 | 100% |
| RESIDENTAIL | 1750.71 | 17 | 15 | 2 | 88% |
Construction Progress
THE ROYAL TUSK
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt100%
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%