List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

THE WHITE VILLAS KASARA

by St. Angelo's VNCT Ventures Pvt. Ltd.
Certificate SignedP51700018232
THE WHITE VILLAS KASARAProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700018232
Developer
St. Angelo's VNCT Ventures Pvt. Ltd.
Architect
TANGENT ARCHITECT
Project Bank
STATE BANK OF INDIA
Proposed Possession
2027-12-31
Revised Possession
1900-01-01
Extended Possession
2025-12-31
Total Units
20
Units Sold
18 (90%)
Buildings
20
Project Area
2848.12 sq.m
Total FSI
2239.66
MahaRERA QR
THE WHITE VILLAS KASARA
MahaRERA — P51700018232
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🔢Total Units1
🏡Residential1

Apartment Configurations

ASTER 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK86.62110
100%

ASTER 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK93.89110
100%

ASTER 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK86.62110
100%

DAISY 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83101
0%

DAISY 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83101
0%

IRIS 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

IRIS 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

JASMINE 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

JASMINE 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

LAVENDER 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

LAVENDER 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

MARIGOLD 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

MARIGOLD 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

NIGELLA 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

NIGELLA 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

ORCHID 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.55110
100%

ORCHID 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

SUNFLOWER

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.55110
100%

TULIP 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

TULIP 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK92.83110
100%

Construction Progress

ASTER 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

ASTER 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ASTER 3

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

DAISY 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

DAISY 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

IRIS 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

IRIS 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

JASMINE 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

JASMINE 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

LAVENDER 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

LAVENDER 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

MARIGOLD 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

MARIGOLD 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

NIGELLA 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

NIGELLA 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ORCHID 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ORCHID 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

SUNFLOWER

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

TULIP 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

TULIP 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings20%
Electrical meter room, sub-station, receiving station100%
Energy managemcnt100%
Fire protection and fire safety requirements
Internal Roads & Footpaths50%
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal50%
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water
Water Supply100%
Water conservation /Rain water harvesting