Tulip N1 N2 N3 O1

by Royale Urbanspace Partnership
Certificate SignedP51700019737
Tulip N1 N2 N3 O1Project photos will appear here when available.

Project Information

RERA Certificate No.
P51700019737
Registration No.
REA51700053144
Registration Date
2026-02-16
Developer
Royale Urbanspace Partnership
Architect
TRIARCH DESIGN STUDIO
Project Bank
PUNJAB NATIONAL BANK
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
99
Units Sold
22 (22%)
Buildings
4
Project Area
859.18 sq.m
Total FSI
3902.81
Approved FSI
3902.81
MahaRERA QR
Tulip N1 N2 N3 O1
MahaRERA — P51700019737
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🏠Habitable5
🔢Total Units18
🏡Residential18
🏗️Proposed Floors6
Sanctioned6
🏠Habitable5
🔢Total Units27
🏡Residential27
🏗️Proposed Floors6
Sanctioned6
🏠Habitable5
🔢Total Units27
🏡Residential27
🏗️Proposed Floors6
Sanctioned6
🏠Habitable5
🔢Total Units27
🏡Residential27

Apartment Configurations

TULIP 01

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.8218018
0%

TULIP N1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.0827027
0%

TULIP N2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.0827027
0%

TULIP N3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.0827027
0%

Construction Progress

TULIP 01

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
Stilt Floor0%

TULIP N1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
Stilt Floor0%

TULIP N2

Basement (if any)0%
Excavation5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

TULIP N3

Basement (if any)0%
Excavation5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting