Tulsi Centre PointProject photos will appear here when available.
Project Information
RERA Certificate No.
P52000000571
Registration No.
REA52000004323
Registration Date
2017-07-18
Developer
Navkar developers Partnership
Architect
Siddarth Shrish Shirur
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2021-12-30
Revised Possession
2019-12-31
Extended Possession
2021-12-30
Units Sold
0
Buildings
1
Project Area
5859.50 sq.m
Total FSI
6774.33
Approved FSI
6306.33
Tulsi Centre Point
MahaRERA — P52000000571
MahaRERA — P52000000571
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors8
✅Sanctioned8
Apartment Configurations
tulsicentrepoint
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 28.19 | 34 | 14 | 20 | 41% |
| 1BHK | 29.22 | 14 | 4 | 10 | 29% |
| 1BHK | 30.12 | 17 | 9 | 8 | 53% |
| 1BHK | 32.98 | 2 | 0 | 2 | 0% |
| 1BHK | 33.72 | 4 | 0 | 4 | 0% |
| 1BHK | 35.58 | 3 | 0 | 3 | 0% |
| 1RK | 17.61 | 5 | 5 | 0 | 100% |
| 1RK | 19.08 | 1 | 1 | 0 | 100% |
| 1RK | 20.44 | 13 | 11 | 2 | 85% |
| 2BHK | 42.11 | 19 | 12 | 7 | 63% |
| 2BHK | 44.16 | 5 | 5 | 0 | 100% |
| 3BHK | 63.54 | 1 | 0 | 1 | 0% |
| OFFICE | 6.52 | 2 | 1 | 1 | 50% |
| OFFICE | 7.98 | 1 | 1 | 0 | 100% |
| OFFICE | 8.42 | 4 | 0 | 4 | 0% |
| OFFICE | 9.38 | 2 | 1 | 1 | 50% |
| OFFICE | 10.75 | 3 | 0 | 3 | 0% |
| OFFICE | 11.41 | 4 | 3 | 1 | 75% |
| OFFICE | 12.81 | 7 | 0 | 7 | 0% |
| OFFICE | 13.06 | 1 | 0 | 1 | 0% |
| OFFICE | 13.74 | 4 | 0 | 4 | 0% |
| OFFICE | 14.64 | 1 | 1 | 0 | 100% |
| OFFICE | 15.49 | 2 | 0 | 2 | 0% |
| OFFICE | 16.38 | 9 | 2 | 7 | 22% |
| OFFICE | 17.41 | 1 | 0 | 1 | 0% |
| OFFICE | 18.18 | 4 | 0 | 4 | 0% |
| OFFICE | 19.45 | 3 | 1 | 2 | 33% |
| SHOP | 6.6 | 2 | 1 | 1 | 50% |
| SHOP | 8.43 | 4 | 3 | 1 | 75% |
| SHOP | 9.38 | 1 | 0 | 1 | 0% |
| SHOP | 10.77 | 3 | 0 | 3 | 0% |
| SHOP | 11.71 | 1 | 0 | 1 | 0% |
| SHOP | 13.36 | 8 | 1 | 7 | 12% |
| SHOP | 14.05 | 1 | 0 | 1 | 0% |
| SHOP | 14.99 | 8 | 0 | 8 | 0% |
| SHOP | 15.84 | 1 | 0 | 1 | 0% |
| SHOP | 16.79 | 5 | 0 | 5 | 0% |
| SHOP | 17.72 | 2 | 0 | 2 | 0% |
| SHOP | 18.44 | 8 | 3 | 5 | 38% |
| SHOP | 19.55 | 2 | 0 | 2 | 0% |
| SHOP | 20.67 | 1 | 1 | 0 | 100% |
| SHOP | 26.5 | 1 | 1 | 0 | 100% |
Construction Progress
tulsicentrepoint
RERA Registered Amenities
✅Aggregate area of recreational Open Space
✅Community Buildings85%
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking1%
✅Sewerage (Chamber, Lines, Septic Tank , STP)30%
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
⬜Water conservation /Rain water harvesting