UTSAV CITY PHASE III

by TODAY MICRON DEVELOPERS Partnership
Certificate SignedP52000019069
UTSAV CITY PHASE IIIProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000019069
Registration No.
REA52000047693
Registration Date
2022-08-12
Developer
TODAY MICRON DEVELOPERS Partnership
Architect
Swapnil Kalyankar Architect
Project Bank
ICICI BANK LIMITED
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
2023-12-30
Units Sold
0
Buildings
3
Project Area
10446.80 sq.m
Total FSI
9870.41
Approved FSI
7263.21
MahaRERA QR
UTSAV CITY PHASE III
MahaRERA — P52000019069
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors8
✅Sanctioned8

Apartment Configurations

BUILDING NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.1528280
100%
2 BHK41.8428280
100%

BUILDING NO 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.8128280
100%
1 BHK30.1528280
100%

NOT APPLICABLE

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK—000
0%

Construction Progress

BUILDING NO 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

NOT APPLICABLE

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting