VRINDAVAN COMPLEX

by PATIL BUILDERS Partnership
Certificate SignedP99000000827
VRINDAVAN COMPLEXProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000000827
Registration No.
REA99000004777
Registration Date
2017-07-24
Developer
PATIL BUILDERS Partnership
Architect
Yogesh Mhatre Sairachana
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2020-11-30
Revised Possession
2019-05-31
Extended Possession
2020-11-30
Units Sold
0
Buildings
2
Project Area
1509.00 sq.m
Total FSI
4255.00
Approved FSI
3875.00
MahaRERA QR
VRINDAVAN COMPLEX
MahaRERA — P99000000827
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6

Apartment Configurations

VRINDAVAN COMPLEX BUILDING NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK31.08202
0%
1BHK32.081293
75%
2BHK39.74431
75%

VRINDAVAN COMPLEX BUILDING NO 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK31.08211
50%
1BHK32.081275
58%
2BHK39.74431
75%

Construction Progress

VRINDAVAN COMPLEX BUILDING NO 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

VRINDAVAN COMPLEX BUILDING NO 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting100%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%