Xrbia Warai / Neral - Ph 2

by XRBIA WARAI DEVELOPERS PRIVATE LIMITED Company
Certificate SignedP52000004499
Xrbia Warai / Neral - Ph 2Project photos will appear here when available.

Project Information

RERA Certificate No.
P52000004499
Registration No.
REA52000007983
Registration Date
2020-06-13
Developer
XRBIA WARAI DEVELOPERS PRIVATE LIMITED Company
Architect
Ajay Gade
Project Bank
HDFC BANK
Proposed Possession
2022-12-29
Revised Possession
2021-06-30
Extended Possession
2022-12-29
Units Sold
0
Buildings
20
Project Area
9127.00 sq.m
Total FSI
49990.61
Approved FSI
49990.61
MahaRERA QR
Xrbia Warai / Neral - Ph 2
MahaRERA — P52000004499
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
✅Sanctioned9
🏗️Proposed Floors9
✅Sanctioned9
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors7
✅Sanctioned7
🏗️Proposed Floors7
✅Sanctioned7
🏗️Proposed Floors7
✅Sanctioned7
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors9
✅Sanctioned9
🏗️Proposed Floors9
✅Sanctioned9
🏗️Proposed Floors9
✅Sanctioned9

Apartment Configurations

A3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK19.3432284
88%
1 BHK21.3540319
78%

A4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK19.3432302
94%
1 BHK21.3540373
92%

B4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.3541383
93%

C1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK31.82817
12%
2 BHK32.8913121
92%
2 BHK33.42330
100%
2 BHK33.51880
100%
2 BHK33.69110
100%
2 BHK33.7220
100%
2 BHK34.65110
100%
2 BHK34.99220
100%
2 BHK35.25808
0%
2 BHK35.27220
100%
2 BHK35.42321
67%
2 BHK35.44523
40%

C2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK31.82808
0%
2 BHK31.96440
100%
2 BHK32.8922220
100%
2 BHK34.6522517
23%

C3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK31.39808
0%
2 BHK31.96514
20%
2 BHK33.07330
100%
2 BHK33.5121165
76%
2 BHK34.6517017
0%
2BHK35.08211
50%

C4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK29.99110
100%
2 BHK31.58110
100%
2 BHK32.2990
100%
2 BHK32.27101
0%
2 BHK32.5550
100%
2 BHK32.67110
100%
2BHK32.88211
50%
2BHK34.56624
33%
2BHK34.78431
75%

C6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK31.41211
50%
2 BHK34.6422211
95%
2 BHK34.66330
100%
2 BHK35.41880
100%
2 BHK35.44550
100%

C8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK36.8524213
88%
2 BHK38.89871
88%
2 BHK41.11826
25%

C9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK36.8524240
100%
2 BHK38.89880
100%
2 BHK41.11844
50%

D8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK46.8128271
96%
2 BHK49.06440
100%
2 BHK50.11835
38%

E1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK43.44330
100%
3 BHK46.0440
100%
3 BHK46.39550
100%
3 BHK46.66660
100%
3 BHK46.84743
57%
3 BHK47.81019
10%
3 BHK48.82514
20%

F1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK52.0940364
90%

K1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK19.32440
100%
1 BHK22.931073
70%
1 BHK27.01110
100%
1 BHK27.01553619
65%

K2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK19.32440
100%
1 BHK22.931091
90%
1 BHK27.01563521
62%

K3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK19.32844
50%
1 BHK22.9320713
35%
1 BHK27.0142357
83%

K4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK19.32862
75%
1 BHK22.93201010
50%
1 BHK27.0142357
83%

K6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK26.731261188
94%

K7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK26.7312610917
87%

K8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK26.731265076
40%

Construction Progress

A3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises57%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises40%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
Stilt Floor0%

A4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises57%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises40%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
Stilt Floor0%

B4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises85%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
Stilt Floor0%

C1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.88%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises62%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises40%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
Stilt Floor0%

C2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises66%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises43%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks66%
Stilt Floor0%

C3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.79%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises32%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
Stilt Floor0%

C4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.78%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises28%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
Stilt Floor0%

C6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.43%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises94%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises62%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks94%
Stilt Floor0%

C8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises91%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks81%
Stilt Floor0%

C9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.43%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises73%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks93%
Stilt Floor0%

D8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks93%
Stilt Floor0%

E1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises43%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
Stilt Floor0%

F1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.55%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises76%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises43%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks78%
Stilt Floor0%

K1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises83%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
Stilt Floor0%

K2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises83%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks94%
Stilt Floor0%

K3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.88%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises65%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks81%
Stilt Floor0%

K4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.88%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises88%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises43%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks79%
Stilt Floor0%

K6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.88%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises91%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises47%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks87%
Stilt Floor0%

K7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises28%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
Stilt Floor0%

K8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure11%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Club House15%
✅Common Car Parking Spaces10%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station50%
⬜Energy managemcnt
✅Fire protection and fire safety requirements50%
✅Gymnasium
✅Internal Roads & Footpaths50%
✅Kids Play Area90%
✅Landscaping & Tree Planting25%
✅Open Parking20%
✅Sewerage (Chamber, Lines, Septic Tank , STP)50%
⬜Shuttle Bus Service
✅Solid Waste Management And Disposal
✅Storm Water Drains20%
✅Street Lighting50%
✅Swimming Pool
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply80%
✅Water conservation /Rain water harvesting30%