Proposed Possession
2028-07-31
Units Sold
0
Project Area
2470.00 sq.m
Total FSI
5373.03
Approved FSI
5373.03
MahaRERA QR
YASH APARTMENTS
MahaRERA โ€” P52000077341
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿš—Open Parking47
๐Ÿ…ฟ๏ธClosed Parking24
๐Ÿ“…Completion2028-07-31
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿš—Open Parking34
๐Ÿ…ฟ๏ธClosed Parking19
๐Ÿ“…Completion2028-07-31

Apartment Configurations

A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.8421021
0%
1 BHK32.95707
0%
1 BHK34.19707
0%
1 BHK35.42707
0%
2 BHK50.24707
0%
2 BHK53.0121021
0%

B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.8412012
0%
1 BHK33.1808
0%
1 BHK33.33303
0%
1 BHK34.53303
0%

Construction Progress

A wing

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

B wing

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical Meter Room, Sub-Station, Receiving Station
โฌœEnergy management
โฌœFire Protection And Fire Safety Requirements
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Conservation, Rain water Harvesting
โœ…Water Supply
CallWhatsApp
โœ‰๏ธ

Get in Touch

Our team will connect with you shortly

+91
๐Ÿ”’ Your details are secure with us
โšก If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now