YASHWANT SANKALP- Jasmin Phase 2Project photos will appear here when available.
Project Information
RERA Certificate No.
P99000021693
Developer
MAHALAXMI INFRA
Architect
NISHANT PATIL VASTU SHILP SSOCIATES
Project Bank
BASSEIN CATHOLIC BANK
Proposed Possession
2025-07-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
50
Units Sold
42 (84%)
Buildings
1
Project Area
1915.46 sq.m
Total FSI
2000.00
YASHWANT SANKALP- Jasmin Phase 2
MahaRERA — P99000021693
MahaRERA — P99000021693
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors5
✅Sanctioned5
🏠Habitable5
🔢Total
Units50
🏡Residential50
Apartment Configurations
JASMIN Phase 2
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| FLAT | 23.62 | 2 | 0 | 2 | 0% |
| FLAT | 26.98 | 28 | 0 | 28 | 0% |
| FLAT | 28.56 | 4 | 0 | 4 | 0% |
| FLAT | 31.66 | 5 | 6 | -1 | 120% |
| FLAT | 33.23 | 1 | 0 | 1 | 0% |
| FLAT | 38.04 | 4 | 0 | 4 | 0% |
| FLAT | 40.61 | 4 | 0 | 4 | 0% |
| FLAT | 42.72 | 1 | 0 | 1 | 0% |
| FLAT | 47.75 | 1 | 0 | 1 | 0% |
Construction Progress
JASMIN Phase 2
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths50%
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)30%
⬜Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting50%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting