Sadguru Complex Bldg No 9

by Sadguru Builders Partnership
Certificate SignedP51700007141
Sadguru Complex Bldg No 9Project photos will appear here when available.

Project Information

RERA Certificate No.
P51700007141
Registration No.
REA51700014451
Registration Date
2021-09-09
Developer
Sadguru Builders Partnership
Architect
Bac Planner And Engineer
Project Bank
AXIS BANK
Proposed Possession
2029-04-30
Revised Possession
2028-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
247.76 sq.m
Total FSI
2633.78
Approved FSI
194.48
MahaRERA QR
Sadguru Complex Bldg No 9
MahaRERA — P51700007141
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors16
✅Sanctioned16

Apartment Configurations

SADGURU COMPLEX BLDG NO 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.0826125
4%
1.5 BHK42.128325
11%

Construction Progress

SADGURU COMPLEX BLDG NO 9

Basement (if any)80%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

RERA Registered Amenities

✅Aggregate area of recreational Open Space10%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station50%
✅Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains50%
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting