Akhand Phase 3Project photos will appear here when available.
Project Information
RERA Certificate No.
PM1244042601396
Registration No.
PM1244042601396
Registration Date
2026-07-31
Developer
TECHTON LIFESPACES LLP Partnership
Proposed Possession
2031-04-30
Revised Possession
2030-12-31
Total Units
546
Units Sold
0 (0%)
Buildings
3
Project Area
37327.55 sq.m
Akhand Phase 3 MahaRERA โ PM1244042601396
Scan to verify on MahaRERA portal
Wing-wise Details
๐๏ธProposed Floors34
โ Sanctioned34
๐ Habitable32
๐ขTotal
Units186
๐กResidential186
๐๏ธProposed Floors34
โ Sanctioned34
๐ Habitable34
๐ขTotal
Units164
๐กResidential154
๐ขNon-Residential10
๐๏ธProposed Floors34
โ Sanctioned34
๐ Habitable34
๐ขTotal
Units196
๐กResidential186
๐ขNon-Residential10
Construction Progress
Building 8, Wing L - 1(BULG)
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth20%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
Building 8, Wing M - 5(BULG)
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor20%
Building 8, Wing N - 6(BULG)
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
RERA Registered Amenities
โ Aggregate area of recreational Open Space
โ Community Buildings
โ Electrical meter room, sub-station, receiving station
โ Energy managemcnt
โ Fire protection and fire safety requirements
โฌInternal Roads & Footpaths
โ Landscaping & Tree Planting
โ Open Parking
โ Sewerage (Chamber, Lines, Septic Tank , STP)
โ Solid Waste Management And Disposal
โ Storm Water Drains
โ Street Lighting
โ Treatment And Disposal Of Sewage And Sullage Water