List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Amakin Mohammadiya Complex Phase Iii

by Raj Corporation Partnership
Certificate SignedP51700010706
Amakin Mohammadiya Complex Phase IiiProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700010706
Registration No.
REA51700019857
Registration Date
2021-09-09
Developer
Raj Corporation Partnership
Architect
Ar. Uday R Satavalekar
Project Bank
BANK OF BARODA
Proposed Possession
2024-12-30
Revised Possession
2024-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
19710.77 sq.m
Total FSI
62041.83
Approved FSI
19567.63
MahaRERA QR
Amakin Mohammadiya Complex Phase Iii
MahaRERA โ€” P51700010706
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors38
โœ…Sanctioned38
๐Ÿ—๏ธProposed Floors35
โœ…Sanctioned35
๐Ÿ—๏ธProposed Floors35
โœ…Sanctioned35

Apartment Configurations

A5 HUSAMI B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK54.97382414
63%
2BHK55.27331320
39%
2BHK56.92381919
50%

B3 NOORANI A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.5919910
47%
1BHK32.919811
42%
1BHK32.91721755
24%

B4 NOORANI B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.5919514
26%
1BHK32.919415
21%
1BHK32.91722844
39%

Construction Progress

A5 HUSAMI B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.12%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises24%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks32%
Stilt Floor10%

B3 NOORANI A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%

B4 NOORANI B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โœ…Community Buildings100%
โœ…Electrical meter room, sub-station, receiving station
โœ…Energy managemcnt
โœ…Fire protection and fire safety requirements
โœ…Internal Roads & Footpaths
โœ…Landscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โœ…Treatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now