A
✓ MahaRERA P51800034461RERA: no litigation reported19
Units
2024
Possession
1
Buildings
Kept in Abeyance
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New Project · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Dec 2024
Status
New Project
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
2 BHK683–812 ft²On request
3 BHK899–1,115 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51800034461
Registered
—
Litigation
No reported in source
Escrow Bank
AXIS BANK LTD
Architect
—
Total FSI
4501
04
Buildings · 1 Wing(s)
Andheri Shilpa Chs— floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Village Gundavali
▸ Explore map & Street View — for verified buyers
09
Construction Progress
10% avgExcavation100%
Overall Percentage of Completion of the work done For the entire Building /Wing10%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by New India Construction Company
?
Frequently Asked Questions
When is possession of Andheri Shilpa Chs?
As per MahaRERA, proposed possession is Dec 2024.
Is Andheri Shilpa Chs RERA-registered?
Yes — MahaRERA registration P51800034461. The current MahaRERA source record reports no litigations.
Who is the developer?
New India Construction Company — 7 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.